Construction of Chivala Police Unit Staff House


Construction of Chivala Police Unit Staff House

Construction of Chivala Police Unit Staff House

Start date: 2024-06-09 Due date: 2024-12-31 Approval date: 2024-04-25 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
106,549,703.88   MWK
Total Budget
2025-05-23
Date Created
2025-05-23
Last updated
Construction
Project Type
Completion
Project Status

Locations

Description Dowa South East
District Dowa
Region Central
Street address
Postal code

Documents

Title Construction of Chivala Police Unit Staff House
Description Construction of Chivala Police Unit Staff House
Document Type Award notice
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description World Bank
Locality Washington, DC
Region District of Columbia
Street address 1818 H Street, NW Washington, DC 20433 USA
Postal code 20433
Country United States of America (the)
Telephone +1 (202) 473-1000
Fax Number
URL www.worldbank.org
Roles Funder
Description The World Bank is an international financial institution that provides loans and grants to the governments of low- and middle-income countries for the purpose of pursuing capital projects. It comprises two institutions: the International Bank for Reconstruction and Development (IBRD), and the International Development Association (IDA). The World Bank is a component of the World Bank Group.
Description South gate construction
Locality Lilongwe
Region
Street address Lilongwe
Postal code
Country Malawi
Email @gmail.com
Telephone 0000
Fax Number
URL
Roles Contractor
Description
Description Dowa District Council
Locality Dowa
Region Central
Street address Private Bag 2
Postal code Dowa
Country Malawi
Telephone 0999632510
Fax Number
URL
Roles Administrative Entity
Description Description

Contracts

OCID MW-DDC-381538-CM-RFQ
External Reference
Title Contract
Description Budget
Status Active
Contract Value MWK 106,549,703.88
Cost Estimate 106,549,703.88
Final Value 0.00
Start Date 2024-06-10
End Date 2024-11-09
Max Extent Date
Duration In Days 152
Procurement Method
Method Details
Procuring Entity
Administrative

Documents

No records were added

Modifications

No records were added

Budget

Description Budget
Amount MWK 106,549,703.88
Start Date 2024-06-10
End Date 2024-11-09
Max Extent Date 2024-12-31
Duration In Days 204
Party ID Dowa District Council-Dowa-MW
URI

Project Funding

Party World Bank-Washington, DC-US
Amount MWK 106,549,703.88
Description
No comments added

Environment

No record was added

Completion

End Date: 2024-11-09
End Details: Construction of Chivala Police Unit Staff House
Final Scope: Construction of Chivala Police Unit Staff House
Final Scope Details: Construction of Chivala Police Unit Staff House
Final Value Amount: 0.00
Final Value Details: Construction of Chivala Police Unit Staff House

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2024-06-10
End Date 2024-11-09
Max End Date 2024-12-31