Construction of Teacher's House at Namutegha Primary School


Construction of the modern teacher's house at Namutegha Primary School

To provide a conducive habitable dwelling residence for teachers hence reducing the pupil-teacher ratio and consequently improving the educational attainment of learners

Start date: 2022-12-22 Due date: 2023-06-30 Approval date: 2022-12-15 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
30,422,465.36   MWK
Total Budget
2023-06-02
Date Created
2023-06-02
Last updated
Construction
Project Type
Completion
Project Status

Locations

No records were added

Documents

Title Picture
Description The project at the finishing level
Document Type Defaults
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Contract
Description The Project contract document between Chitipa District Council and Bufama Building Contractors
Document Type Signed Contract
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Bufuma Building Contractors
Locality Chitipa
Region North
Street address Chitipa street
Postal code
Country Malawi
Telephone 0000
Fax Number 0000
URL
Roles Contractor
Description Bufuma provides Construction services that cater for the public and private sector. The company also offers building project management solutions that are tailored to help its clients meet all applicable requirements in construction.

Contracts

OCID Contract/15/12/22
External Reference
Title Contract
Description Project contract document
Status Active
Contract Value MWK 30,422,645.36
Cost Estimate MWK 30,422,645.36
Final Value 0.00
Start Date 2022-12-22
End Date 2023-03-22
Max Extent Date
Duration In Days 90
Procurement Method Open
Method Details Lowest cost
Procuring Entity Chitipa District Council-Chitipa-MW
Administrative Chitipa District Council-Chitipa-MW

Documents

No records were added

Modifications

No records were added

Budget

Description The Funding is from GESD and it comprises of Substructure 30%, Superstructure and roof 35%, finishing and retention 35%
Amount MWK 30,442,645.36
Start Date 2022-12-22
End Date 2023-03-22
Max Extent Date
Duration In Days 90
Party ID Chitipa District Council-Chitipa-MW
URI

Project Funding

Party National Local Goverment-Lilongwe-MW
Amount MWK 30,422,645.36
Description The project is funded by the performance-based grant- GESD
No comments added

Environment

No record was added

Completion

End Date: 2023-05-18
End Details: The structure is finally built with minor completion works remaining
Final Scope: The completion certificate not issued
Final Scope Details: Painting, glazing, drainage works, doors and locks fixing
Final Value Amount: MWK 30,422,645.36
Final Value Details: MK30,422,645.36

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2023-07-14
End Date 2123-07-14
Max End Date

© 2025, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;