construction of a solar powered water reticulated system at Beni Health Centre, Chigodi Health Centre and Chitsime Health Centre

        Return back Please wait...
image

construction of a solar powered water reticulated system at Beni Health Centre, Chigodi Health Centre and Chitsime Health Centre

construction of drilling of a borehole, construction of a tank stand and installation of a solar powered water reticulated system

to provide potable water to the health centres to aid in their day to day activities

Start date: 2024-08-12 Due date: 2025-04-10
155,000,000.00   MWK
Total Funding
2023-03-06
Approval date
2025-03-14
Last updated
construction
Project Type
Implementation
Project Status

Locations

DESCRIPTION DISTRICT REGION ADDRESS
Beni Health Centre in T/A Masula Lilongwe Central
Chigodi Health Centre in T/A Mazengera Lilongwe Central
Chitsime Health Centre in T/A Kalumba Lilongwe Central