Project

Construction of Chanunkha CDSS School Blocks and furnishing with students desks and teachers chairs and desks

image

Construction of Chanunkha CDSS School Blocks and furnishing with students desks and teachers chairs and desks


The project involved construction of a classroom block furnished with desks

To enable students learning in a contusive environment

Start date: 2022-11-07 Due date: 2022-12-31 Approval date: 2022-12-02 Orange Category (7 Red Flags)
Absence of a clear feasibility study Limited assessment of environmental impacts Limited assessment of social impacts Limited assessment of economic impacts Weak stakeholder engagement Limited competition Lack of maintenance plans
58,940,486.46   MWK
Total Budget
2023-09-06
Date Created
2023-09-06
Last updated
Construction
Project Type
Completion
Project Status

Locations

No records were added

Documents

No records were added

Parties

No records were added

Contracts

No records were added

Budget

No records were added

Project Funding

No records were added
No comments added

Environment

No record was added

Completion

End Date: 2023-01-08
End Details: The project was built and furnished with desks
Final Scope: Classroom block constructed and desks provided
Final Scope Details: 1 classroom block and 120 desks provided
Final Value Amount: MWK 58,940,486.46
Final Value Details: Fifty eight million nine hundred forty thousand four hundred eighty six kwacha forty six tambala

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2022-11-07
End Date 2023-01-08
Max End Date 2023-01-08